Now the whole area voucher application has been approved, Route 1 is no longer ‘on hold’ and the ordering / blowing of fibre is being worked into B4RN’s plans and will proceed as soon as possible.
We also have dates for the 2 road crossings on Hesley Lane which are planned as
29th April – Old school field crossing
1st May – Gawthorpe House crossing
The crossing at the Reading Room to the lane beside the church has been quoted for and so should follow in the next batch of planned work during May or early June
The control node cabinet is now in place on its concrete base in the Reading Room car park, which is another major step forward.
Digging has also still been under way and ducting is now in place up to Swainstead incorporating the first stretch of the route towards Sheepwash and Wham.