4th April 2019 update

Now the whole area voucher application has been approved, Route 1 is no longer ‘on hold’ and the ordering / blowing of fibre is being worked into B4RN’s plans and will proceed as soon as possible.

We also have dates for the 2 road crossings on Hesley Lane which are planned as

29th April – Old school field crossing

1st May – Gawthorpe House crossing

The crossing at the Reading Room to the lane beside the church has been quoted for and so should follow in the next batch of planned work during May or early June

The control node cabinet is now in place on its concrete base in the Reading Room car park, which is another major step forward.

Digging has also still been under way and ducting is now in place up to Swainstead incorporating the first stretch of the route towards Sheepwash and Wham.